creation of bom and after running mrprun, planned orders are not in md04

Former Member
0 Kudos

Dear Sap Gurus,

I had created a bom for finished product which contains semifinished product and rawmateria. so a finished product bom and semifinished product created.

I had run mrp md51 for finished product and it has displayed so materials exist for the finished product and i check in md04 only reservation for the network is displayed but planned order is not displayed so due to this i am unable to raise purchase requisitions and unable to do conversion of planned order to production order.

Is there no way to do conversion of planned order to production order through order reservation.

So, I kindly request anybody to help me how to get the planned order after running the mrp.

regards,

muralidhar putta.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

my problem is solved

virendra_pal
Active Contributor
0 Kudos

check you material master data for procurement type (MRP 2 tab) - should be inhouse

also you need to ensure that relevant config is there for creation of planned order of the correct type

it is not simple you need to understand the PS-MM-PP integration

get a senior consultant who knows how to do these things

this forum is not meant for consulting - it is meant to give advise

also note - do not repeat posts - this is similar to the one yesterday, why have you created a new one??, have you closed the old one??

please stick to the basic rules of this forum and respect them