Hi All,

I want to create Sales Plan (SOP) from Historical Consumption Data (given in the Material Master in Forecasting view). The MRP type has also been set to "VV".

However when I try to create a Sales Plan from Forecast (in MC87 - Create Plan) I get the following error message "Error reading consumption data".

Please reply ASAP.

Thanks in advance.

Sameer.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Sameer,

Maintain the consumption data in the additonal data "consumption tab" and try.

Regards

TAJUDDIN

Former Member
0 Kudos

Hi Tajuddin,

I have already maintained the consumption data in the "Consumption" tab.

Are there any settings that need to be done?

Please reply at earliest.

Thanks

Sameer

Former Member
0 Kudos

Sammer

You create a sales plan through forecast in the Sales and Operations

Planning with Transaction MC88, MC76 or MC94 with the planning type

SOPKAPAM or SOPDIS.You have maintained different factory calendars for info

structure S076 (Transaction MC7F) and the planning objects of your plants

(plant calendar).If the horizon of the factory calendar for the plants is

shorter than for info structure S076, the system generates an error message

during forecast:'Error reading consumption data' (MA518) or 'Insoluble

problem reading factory calendar for ID & date &' (MA505).

Cause and Prerequisites

To allow the online-change of the parameters during forecast, sufficient

historical values must be read from the material master.The program has

been designed in a way that all historical data is read which is in the

horizon of the factory calendar for info structure S076. However, the

factory calendar is used for the plant during the import of the consumption

data from the material master.That is why the factory calendar for the

plants must also contain a date for every date from the factory calendar

for info structure S076.

Solution

As mentioned in the cause, the horizon of the factory calendar for the

plants must not be shorter than the horizon of the factory calendar for

info structure S076. During the weekly period, the horizon of the plant

calendar must be longer than that of the factory calendar for information

structure S076 since the beginning of the first week of a year takes place

mostly in the previous year.

Maintain the factory calendar for the plants such that it at least

corresponds to the release period of the factory calendar of the

information structure.

Header Data

Release Status: Released for Customer

Released on: 02.04.2003 12:49:15

Priority: Recommendations/additional info

Category: Consulting

Main Component PP-SOP Sales & Operations Planning

Additional Components:

Former Member
0 Kudos

Sammer

You create a sales plan through forecast in the Sales and Operations

Planning with Transaction MC88, MC76 or MC94 with the planning type

SOPKAPAM or SOPDIS.You have maintained different factory calendars for info

structure S076 (Transaction MC7F) and the planning objects of your plants

(plant calendar).If the horizon of the factory calendar for the plants is

shorter than for info structure S076, the system generates an error message

during forecast:'Error reading consumption data' (MA518) or 'Insoluble

problem reading factory calendar for ID & date &' (MA505).

Cause and Prerequisites

To allow the online-change of the parameters during forecast, sufficient

historical values must be read from the material master.The program has

been designed in a way that all historical data is read which is in the

horizon of the factory calendar for info structure S076. However, the

factory calendar is used for the plant during the import of the consumption

data from the material master.That is why the factory calendar for the

plants must also contain a date for every date from the factory calendar

for info structure S076.

Solution

As mentioned in the cause, the horizon of the factory calendar for the

plants must not be shorter than the horizon of the factory calendar for

info structure S076. During the weekly period, the horizon of the plant

calendar must be longer than that of the factory calendar for information

structure S076 since the beginning of the first week of a year takes place

mostly in the previous year.

Maintain the factory calendar for the plants such that it at least

corresponds to the release period of the factory calendar of the

information structure

thanks

kedar

Answers (1)

Answers (1)

siddheshwar_rajguru2
Active Participant
0 Kudos

HI Sameer,

You maintain consumption data in MM01 and run forcast program from materil master.

Try this and let me know for the same.

Regards

Siddhesh

Former Member
0 Kudos

Hi Siddhesh

In his previous reply he has alredy maintained the data (consumption values0 in forecasting.do u have another solution?

thanks