I have created PIR for pMRP.

RaghavanKathamuthu_0-1723665533052.png

If I run MD01 this will be considered for MRP right?

Then what is the point of releasing the plan in process pMRP app?

RaghavanKathamuthu_1-1723665577938.png

Or am I understanding it wrongly?

View Entire Topic
Caetano
Product and Topic Expert
Product and Topic Expert

Hello

You can create Inactive PIRs (uncheck the Active button), so that they are not relevant for MRP before you run pMRP and validate if your forecast is feasible. You can make changes in your demand plan in pMRP, and then release the PIRs when you are done.

Regards,
Caetano