Counter base maintenance and multiple counter maintenance

Former Member
0 Kudos

Hi

With refering to the counter base order generated in the system, i have confused.

We have the plans 100, 200, 300 to max 2000 Hours. The task lists are assigned. The maintenance plan annual estimate is 4000 Hours (i dont know why its required if the measurment documents are in use) ..

The system is regularely generating the orders eventhough we have measurement docuements upto 300 Hours. Last week we have no measurement updates.

Can you give me the logic, functionality of the performance maintennace. I have read SAP help which is not explaining in practical manner.

Also how to work for multiple counter maintenance. We have to do for DAY (30 Days, 60 days. 180, 360 Days) Wise or Hour wise (300, 900, 1500, 3500, 7000 Hours maintenance. Can you tell me how to work for this on single maintennace plan..since our equipment also only one.

Accepted Solutions (1)

Accepted Solutions (1)

paul_meehan
Employee
Employee
0 Kudos

Hi,

This appears to be a typical multiple counter plan situation consisting of performance based and time based elements. The performance cycles are based on operating hours and time is the elapsed days.

The relevant section of SAP Help is - [here|http://help.sap.com/saphelp_erp60_sp/helpdata/en/d8/e06a1f7e9c144fbb3a3ed0c38bc38a/frameset.htm]

See point 3-Scheduled date calculation. In particular:

The annual performance recorded for the counters and the most up-to-date counter reading are used to calculate the corresponding planned date.

Annual Estimate is used to calculated planned date meaning that calls can occur before the actual counter readings are reached.

-Paul