For matreials with price indicator S we are running costing..in CK40N..

What about materials with V.. How are they costed... what is meant by costing sheet

PLease explain..

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

Cost sheet is used to calculate overheads in costing. The overhead could be labor, vairable and fixed o/h etc,.. In the costiing sheet we have different cost sheet rowns which contains the details of Base(Cost element from where the cost incurred), overhead rate and credited cost center.

V is moving price indicaor in the material master. Generally organization apply this indicator if the material is procured externally and price vaires frequently.

Rg,

Shree...

Former Member
0 Kudos

"V" finished and semifinished products can be costed from PP orders (either from planned or actual costs)

While 'V' materials get the average price from purchase orders.

cheers