hi friends,

i am facing problem with costing run. this is running good till marking then i sm not able to release it. it says release too early. thats why i edited the costing run date to 01.01.08 but still the same error. please forward ur suggestions. i can also send the screen shots if required. thanks

sanjeev

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

If you have it set for 1/1/08 - you can not release it until 1/1/08

Former Member
0 Kudos

Hi

Hope your date control maintained in the costing variant is causing the error.

If required to release the cost estimate go to OKKN or OKK6 and change the date control for the fileld Valuation Date.

Good Luck