Hello Experts,
I am trying to create primary cost / revenue element with category for Balance sheet account for Materials, as a result system displays the following message:
Case: I need to see commitment values for the materials in project system that is why i am creating statistical cost element for inventory.
Thanks.
Sarim
Hi Sarim,
90 cost element category applicable to Asset and Material GL accounts only not possible for P & L GL accounts. So, please account type as balance sheet.
Thank you,
Madhu