Can any one please send me the configuration doccument which has to be done before KP06 and also doccument on How to upload planning value from Excel-through KP06
Please send me with screenshots to my mail id
manam.sreemannarayana@gmail.com
Points are given to all the gurus
Thanks in advance
Regards
Narayana
Message was edited by:
manam narayana
Hi,
The steps to be followed for Cost Center Planning using excel upload are as under:
1. Define Plan Versions using transaction code OKEV. Settings are to be made for each fiscal year.
2. Define Planning Layouts using transaction code KP65. You can use SAP standard layout or copy the layout and make changes as per the business requirements. In the layout you can include the columns - Cost Center, Cost Element, Fixed Costs etc.
3. Define User defined Planner Profile using transaction code KP34. Please ensure that you select the check box "Integrated Excel" in the tab Layouts for Controlling. Also enter the file description.
4. Select the planning profile using transaction code KP04.
5. Upload plan data (with excel file) using Transaction code KP24 / KP06.
You can also go though the following link (SAP Help on Cost Center Planning:
http://help.sap.com/saphelp_46c/helpdata/en/5b/d2200743c611d182b30000e829fbfe/frameset.htm
Thanks
Murali.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
6 | |
6 | |
6 | |
5 | |
5 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.