Hi Gurus.,

Can any one please send me the configuration doccument which has to be done before KP06 and also doccument on How to upload planning value from Excel-through KP06

Please send me with screenshots to my mail id

manam.sreemannarayana@gmail.com

Points are given to all the gurus

Thanks in advance

Regards

Narayana

Message was edited by:

manam narayana

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

The steps to be followed for Cost Center Planning using excel upload are as under:

1. Define Plan Versions using transaction code OKEV. Settings are to be made for each fiscal year.

2. Define Planning Layouts using transaction code KP65. You can use SAP standard layout or copy the layout and make changes as per the business requirements. In the layout you can include the columns - Cost Center, Cost Element, Fixed Costs etc.

3. Define User defined Planner Profile using transaction code KP34. Please ensure that you select the check box "Integrated Excel" in the tab Layouts for Controlling. Also enter the file description.

4. Select the planning profile using transaction code KP04.

5. Upload plan data (with excel file) using Transaction code KP24 / KP06.

You can also go though the following link (SAP Help on Cost Center Planning:

http://help.sap.com/saphelp_46c/helpdata/en/5b/d2200743c611d182b30000e829fbfe/frameset.htm

Thanks

Murali.