Dear All,

My client wants to use WBS elements instead of Cost Center. Can WBS elements can be mapped under Profit Centers ?

Business Areas, Profit Centers, Cost Centers, Plants, WBS elements - can we use all or some to be eliminated ?

Thanks,

JEERI

Moderator: Please, avoid asking basic questions

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Jeeri,

the answer is yes to both questions.

Please see SAP notes 41103 and 106968 explaining in detail the CO account assignment

logic.

br, Guido

Former Member
0 Kudos

hi,

Yes you can create WBS eleemnt and assign profit center.