Dear Experts,

My requirement is cost center splitting. I configured all settings related splitting & splitting price calculation like as below,

Splitting Structure, Splitting rules and Splitting cost elements with concern activity in Assignment.

Also maintained KP26 - Cost Center with Activity Price.

KP06 - Cost Center and Activity with Cost Element Plan Value.

After done all above things, When I executing Splitting in Front end not coming values and prices.

Where I have done mistake Pl do the needful.

Regards,

KBR.I

Accepted Solutions (0)

Answers (2)

Answers (2)

venkatasatyakrishna_achan
Active Contributor
0 Kudos

you need to assign the splitting structure to cost center use the transaction code OKEW

click on change button, select non assigned cost center, keep the cursor on splitting structure, click on assign button

former_member588855
Active Contributor
0 Kudos

Hi,

In cost center splitting report you get the activity and amount split on those activities.

In KP26 you maintain the cost center and activity combination. what you enter is quantity not price which is supposed to be calculated automatically after price calculation.

Kindly check thoroughly and revert.