on 2012 May 31 8:39 AM
HI
We have 2 plants 0001 & 0002. We have cost centers maintained like 0001_xxxx for plant 0001 and 0002_yyyy for plant 0002.
We want to restrict user creating PO for plant 0001 not to mistakently pick up cost center of plant 0002.
How shall we do this?
Regards
Amit
there is authorization object K_CCA in ME21N. pl chec k with your basis team how it can be used for authorization restrictions