on 2008 May 15 8:23 PM
Hi all
i have a cost ctr 3200, activity type 700000- machine hrs,701000 labours hrs,702000setup hrs,Second cost element700000-machine cost,701000 labours cost,702000setup cost.Primary cost element is 409300and the planned Fixed cost is 75000 in this elemet,.
Activity output planning for 3200 cost center
ct typ Pl.Actual capacity FPrice Vprice
700000 3000 4500 90 160
701000 1800 x x 200
702000 300 x 50 x
Please let me know how to calculate
1)Activity output price planning, 2)Activity dependant planning,3)activity indipendent planning,
Note. i am using sapall planner profile, HOW DO WE ARRIVE IN THE FIGURE?
thanks in advance,
prasad
To keep it simple, Do your cost element planning with KP06.
Activity output planning through KP26 and Calculate the planned activity price through KSPI.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
102 | |
8 | |
6 | |
6 | |
5 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.