Cost Center Committment-Budget Check Error

Former Member
0 Kudos

Dear All,

I have created costcenter budget KPZ2 : Rs 10000

and activated committment management. But while passing expense entry more than 10000 system is not giving error/warning message.

I want to make error message. Any help on this.

Best Regards,

Sainath Padamwar

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

hi

you have to maintain tolerence limit for availibility control if u have not maintained.

hope this solves ur query

path is : controlling --> internal order --> budgeting and availibility control --> define tolerance liimits blah blah

regards

sayeed

Former Member
0 Kudos

Dear,

I want to activate budget check against Cost center not Internal order.

Best Regards

Sainath Padamwar

iklovski
Active Contributor
0 Kudos

Hi,

There is no availability control for budget in cost centres. The budget serves purely for reporting purposes.

However, you can pull a trick, by creating statistical internal orders, linking them to relevant cost centres, making budget configuration for those I/O and, then, creating a validation in OKC7 not allowing posting to the relevant cost centres without those I/O.

Regards,

Eli