Hi Experts,

We are a construction company, and we need to control our cost center budget, is there any contradiction between implementing FM and project budget, I mean we should have either this or that, but not have both of them same time, IS THIS CORRECT?

We need to control our budget for the cost center, to avoid exceeding the CC budget.

Can you help me to control my CC budget on GL level plz.

Many Thks

Fadi


Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Please refer below two notes which suggest workaround for having Cost Centre Budgeting:

101030 FAQ: Availability Control for Cost Centers

68366  Active Availability Control for Cost Centers

Having FM & Project Budget can work together also. But ideally if FM is getting implemented it can suffice the need of Project Budgeting also.

Regards,

Jaymin R. Bhatt