Cost Center - Budget Control

Former Member
0 Kudos

We want to have budget control for cost center. We have maintained budget for cost center. (Internal order and PS not active).

While raising PO aganist this cost center if po value exceeds budget of the cost center system should give error.

Anybody have solution on this please let me know.

Thanks in anticipation.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi

You have to maintain the budget profile and availability control limits for cost center, fi commitment management is active in controlling area.

Otherwise, it will done through BADI.