I am trying to change the costs of a project but it seems like there are "fixed" already after some confirmations happened along the project.

I want to find a solution for this and have the project clear when it comes to costs so i can plan the costs agains comfortably. Of course i want a project without costs but retaining WBS, activities and the other elements.

How can i do this?

Thanks

Paulo_Vitoriano
Active Contributor
0 Kudos

Plan cost cannot be fixed with confirmations. That is relevant for the actual cost. So, you should be able to change plan cost on current NWA.

View Entire Topic
0 Kudos

You can achieve it through ECP, create new version which will allow you to have the same structure with two set of planned cost. But if you looking for new project with exact structure, then you can copy the project without copying the ECP.