Copy Project to different CO Version down to activity level

Former Member
0 Kudos

We have tried to copy a project from one CO version to another using transaction CJ9B, but it only copies to the WBS element level. Is there a transaction that will copy a project to a different CO version that included components down to the activity level?

Thanks, Rae

View Entire Topic
Former Member
0 Kudos

during copying from simulation version, actvity level cost will be copied, but not in co version.

ashis