Dear Experts,

How do we copy CCA/COPA assessment plan cycles (rules) to actual?

Coz' there are too many cycles need to be set.

Thanks in advance.

View Entire Topic
ajaycwa1981
Active Contributor
0 Kudos

Hi

Go to KSU1 and specify the Plan Cycle in the reference field...System would copy the same cycle to Actual...

If you have too many cycles, you can create an LSMW recording...

Regards

Ajay M

sanjivag
Explorer
0 Kudos

Hi,

Can I do it other way around - copy actual assessment cycle to plan assessment cycle?

Thanks

Sanjiv

kamalkumar_biswas2
Active Contributor
0 Kudos

Hi Sanjib

  Yes..you can do

Kamal