Convert plan order to process order from MD04

mdgolamrabbani
Explorer
0 Kudos
161

Hi 

Urgent Support Please?

I am Trying to Convert the Plan Order to Process Order But the System Showing the message 

Enter an order type

Message no. CO022

I am Checking the Configuration Step i think all are Ok but I don't Understand where i missing or mistake,Please Help me for the Solution .

Checking T# Code 

MD04
OPJH
COR4
MM02
OPU5
OPPR
OPPQ
COR8

 

mdgolamrabbani_8-1719160386828.png

Enter an order type

Message no. CO022

 

mdgolamrabbani_0-1719159569674.pngmdgolamrabbani_1-1719159895505.pngmdgolamrabbani_2-1719159926691.pngmdgolamrabbani_3-1719160016675.pngmdgolamrabbani_4-1719160071260.pngmdgolamrabbani_5-1719160171413.png

 

Thanks
M.G Rabbani

View Entire Topic
Smax
Advisor
Advisor
0 Kudos

Hi,

if you convert a planned order into a process order the the Prod. Sched. Profile needs to be set to a PI related one.
I guess this is not set right now hence you get the message as PP01 is by standard used.
Set it to PI01 and run it again.

BTW: A order conversion of materials the are PPDS relevant should be performed from PPDS and not from S4.
PPDS is the scheduling leading system and the dates from that system needs to be taken over in the S4core system. In order to keep the ORDID a conversion from PPDS needs to be done. If you convert the order in S4 then a new order is used hence a not ORDID and that "can" lead to a rescheduling.