Hi,

We are using MES(3rd party system) along with SAP PP-PI. for a order under one opration we have two phases. For first phase(110) control recipe destination is 01, and for other one(phase 120) it is M1(MES). Materials are asigned to both the phases. but when i opening Process instruction, it suppose to show only those material which are assigned to phase 120 but instead it is showing all the materials assigned to both 110 and 120. So system is sending to MES those material which we dont want too. Please help what to do....

Rajib

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

ok