Hi,

Is there a configuration on the scenario that, whenever the Activites or Qty to be confirmed is Zero, the system will post a warning message first before they can save it?

THanks gurus!

Accepted Solutions (1)

Accepted Solutions (1)

former_member335796
Active Contributor
0 Kudos

Hi,

This feature is not available in Standard SAP.

But there are number of User Exits you can use for this purpose.

CONFPP01 PP order conf.: Determine customer specific default values

CONFPP02 PP order conf.: Customer specific input checks 1

CONFPP03 PP order conf.: Cust. specific check after op. selection

CONFPP04 PP order conf.: Customer specific input checks 2

CONFPP05 PP order conf.: Customer specific enhancements when saving

CONFPP06 PP Order Confirmations: Actual Data Transfer

CONFPP07 Single Screen Entry: Inclusion of User-Defined Subscreens

Consult your ABAPer to have the appropriate coding as per the logic..

Regards,

Siva