Dear Guru's

In EHP 5 there is tab (Personnel) in order conformation screen which is giving the shift detail, i have set the config but not able to see that in front end screen.

Kindly give your inputs.

Regards,

Pankaj

Accepted Solutions (0)

Answers (3)

Answers (3)

gyanaranjan_rout
Contributor
0 Kudos

hello

goto,production-shop floor control-operation-confirmation -define confirmation parameter

In individual Entry general Tab ,in the shift view

proposal no shift

tick mark shift in header confirmation

In customer specific field , tick header confirmation

no shift means you can give shift accordingly.

In co15 order confirmation screen,

actual data

SHIFT- 2nd shift(e.g)

hope u will understand

regards

Gyana

gyanaranjan_rout
Contributor
0 Kudos

hello

reply you are clear or not.

regards

Gyana

gyanaranjan_rout
Contributor
0 Kudos

hello

1)put t-code OP4A

2)goto new entry

3)Give grouping let eg.88 and name Tata motor shift

4)select it give Work break schedules eg. lunch,dinner and night break (give timing)

5)In Shift definitions give 1st,2nd and 3rd shift.Don't change date.Only give shift time.

6)In Shift sequences give

sequence description day1 day2 day3 day4 day5 day6 day7

3w 3week rotating shift A A A A A A A

3w 3week rotating shift B B B B B B B

3w 3week rotating shift C C C C C C C

SAVE it.

then go to cr02

click capacity header(cap)

give your grouping number

click interval

click insert screen (near choose)

Then add of interval capacity comes

give valid from and valid to date.

in interval give shift sequence 3w

length of cycle 7

number of shift 3

workdays blank

then enter it.then automatic shift you will see.

Former Member
0 Kudos

Dear Gyan,

Thanks for the reply, but i am not asking about the shift sequence, there is a feature in EHP 5 where i can see the shift while conformation.

Regards,