Dear Experts,

We have defined component scrap lets ay 0.05% in bom for each components but in process orders system is showing 100% component scrap or in other words more components scrap defined in bom after issuance. Moreover this problem is not with all orders and Final issue indicator is not set. Please see below process order view of a material where requirement qty is 4.728 and withdraw qty is 1.60 and so the component scrap is 100% and same is showing in CK13N costing, however in BOM we maintained only 0.05%

What could be the reason? And how we resolve this ? and for future orders system should not set component scrap 100% but the defined % in the bom should be the scrap.

Thank you in advance.

Accepted Solutions (1)

Accepted Solutions (1)

0 Kudos

Dear All found the problem. Someone keep changes the scrap % in bom.

Answers (2)

Answers (2)

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

Please share the screen shot of bill of material for same item screen details where you have entered the scrap %.

Do you have Net indicator set in BOM or any assembly scrap is there?

Is there any scarp defined in material master record?

Best Regards,

R.Brahmankar

lingaiahvanam
Active Contributor
0 Kudos

Hi,

Check once again BOM component scrap percentage and confirm if any material quantity calculation for this component?

Is there any changes to the production order header quantity?

Create another process order and check the component scrap percentage update.

Best Regards,