Complete allocation structure Z4 Message no. KD503

Former Member
0 Kudos
9,260

Complete allocation structure Z4

Message no. KD503

Diagnosis

During settlement, the system puts the sender debits into groups (assignments), which are settled using the same settlement cost element. The settlement assignment is made in the allocation structure, which is stored in the settlement rule for the sender (under settlement parameters).

Cost element 90001000 cannot be assigned to a settlement cost assignment in allocation structure Z4, and therefore it cannot be assigned to a settlement cost element.

Procedure

Possible solutions are as follows:

If the posting under cost element 90001000 was made to the sender because of an incorrect entry, and you can reverse the posting, and do not need to update the allocation structure. You only need to reverse the incorrectly assigned posting before repeating the settlement. Exception: For an investment measure with a line item settlement, you need to extend the allocation structure, even after the reversal.

If the posting was made correctly, you can do the following:

a) You can assign a different allocation structure to the sender: In the master data maintenance for the sender, choose "Settlement rule -> Goto -> Settlement parameters" and then enter a different allocation structure.

If necessary, also check whether the correct allocation structure is entered in the settlement profile. The allocation structure is defaulted in the settlement profile when you create sender master data or when you maintain the settlement rule.

You can update allocation structure Z4

Please help resolve error below.

What do I need to reverse?

Is there a different way to enter actual cost for this?

What do you think is missing in my allocation structure?

View Entire Topic
AkifTemel
Newcomer
0 Kudos

Hello,

 

Tcode : Kah2 

 Find the expense type group and add it here .