Commitment report for limit order - by period

siowfong_chen
Contributor
0 Kudos

I am not sure whether this query should falls under this category or Finance. So, please let me know if you think that this question should be moved to the Finance section.

Anyway, my query is I have created a limit/framework purchase order from period 01.10.2008 to 31.11.2008. The delivery date is set to 01.10.2008 by default by the system. When I run the cost center commitment report for period 01.10.2008 to 31.11.2008, I can see the commitments for this PO. However, if I change the period to be from 01.11.208 to 31.11.2008, the commitments are no longer shown on the report. It seems that the system is using the delivery date as the date to show the commitments. Is it correct to say that this is standard behavior? Is there a way to show the commitments running through the validity period set in the PO rather than by the delivery date? Anyone has other options relating to this?

Interested to hear your comments on this.

Cheers!

SF

Accepted Solutions (0)

Answers (2)

Answers (2)

siowfong_chen
Contributor
0 Kudos

Close due to no answer to this.

former_member581212
Active Contributor
0 Kudos

hi,

As per my knowledge the delivery date shown by the system comes from the planned delivery date entered at the material master record...You can check the MMR in MM03...

Pls check ....this would be the one reason...

hope it helps..

Regards

Priyanka.P

siowfong_chen
Contributor
0 Kudos

Hi! I wasn't using any material. Just a limit order with item categor B and acct assignment cat K. Just want to confirm that the KSB2 report is only using the delivery date as the date for reporting and not for the period (which is what we want).

Thanks!

SF