on 2015 Jan 21 1:30 PM
Dear Experts,
We are implementing PM module for one of our client, the scenario is commitment has to update at the time of raising the Service PR and PO.
Is there any functional module and BAPI available to enhance this.
Ex:- Please find the below example
Order | Budget | Actual | Commitment | Allotted | Available |
B10012200700 | 1000 | 00 | 100 | 100 | 1000 |
Thanks & Regards,
Hi,
maybe it would be somehow possible to change the account assignment object atthe PO creation by using a substitution, however the problem is, that it is not possible to post costs to one order and to consume the budget of another order. This is technically not possible and would also not make any sense.
BR Marinko
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
112 | |
8 | |
8 | |
6 | |
6 | |
5 | |
5 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.