Hi all

I have a question about releasing PR. There is a PR with several line items. But some items have been deleted. (For example, A PR is with 10 items. But item 1, 3 and 4 has been deleted). When I use ME55 to release the PR, the system require me to use ME54 - Individual Release of a Purchase Requisition to release PR). Is it standard behavior? Or I can change IMG to slove it. Thank you for your explanation in advance.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

You have to release it individually only as the line item is deleted.

former_member433442
Active Contributor
0 Kudos

Hi,

I hope there is no settings in IMG. Since there are deleted line items collective release is not possible.

Regards,