cancel
Showing results for 
Search instead for 
Did you mean: 

Collective conversion of planned order to one production order

Former Member
0 Kudos
1,140

Dear all,

1. I have N number of pld ord for same material so i need to convert as production order with cumulative quantity.

Because to reduce Issing and confirming and receiving of number of production orders.

2. I need to create Number of production order with diffferent material numbers in one screen with different production order number.

Because per day i need to create more number of production order with different material number. If i create one by one it will consume more time as well as its not practical possible for our business scenario.

Pls let me know any standards are available in SAP.

Regards,

S.Suresh.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

According to my knowledge it's not possible to get only one production order from N no. of planned order.

However, your issue of more no. of production order can be controlled by restricting the generation of production order / material. Say 2 production order / mtl. Unless you close at least one you are not able to create 3rd production order. This control can be given. Pl. discuss with ABAPer / BASIS. ( I am not sure who will do this, but we have done in my previous company).

Madhava

Former Member
0 Kudos

Dear madav,

With the help of abaper i can solve both the issues, before going to that option i need to find out any standards are available.

I appreciate your quick response.

Thanks a lot.

Regards,

S.Suresh.

Former Member
0 Kudos

Hi,

According to me no standard available.

Madhava

dhaval_choksi3
Active Contributor
0 Kudos

Hi Suresh,

With the help of abaper i can solve both the issues, before going to that option i need to
 find out any standards are available.

I don't think this can be done by development and if possible then it is not advisable.If later you will face

any problem due to this development then I don't think SAP will helps you.

Regards,

Dhaval

former_member734007
Participant
0 Kudos

As far as STD SAP goes its not possible to club N planned order into one production order an if it done later on it will be difficult to find th pegged requirement of that particular order. wht u can do is use LOT SIZE in material master to club planned order into weekly,forthnightly,daily,monthly .

Answers (2)

Answers (2)

Former Member
0 Kudos

Dear Suresh,

You can convert Planned Orders into Production order collectively as a mass maintanance in CO41 Tcode.

Revert if any doubt in case using above tcode.

Further if you wish to have one production order against multiple planned orders it is not possible as per Standard SAP.

You can convert to each planned order into individual production order not to single production order.

If you wish clubbed production order then better you use Individual / Collective Indicator as

2 Collective requirements only

Then you will get cumulative planned orders only against each material and you can convert all of them cumulatively to production orders in CO41 as a mass maintanance.

Hope your problem resolves.

Regards,

Tejas

Regards,

Tejas

Former Member
0 Kudos

Dear teja,

Whatever u said right, But i need to convert from pld to prd ord stage only.

Thanks for your response,

Regards,

S.Suresh.

Former Member
0 Kudos

Hi,

You can convert Planned Orders into Production order collectively as a mass maintanance in CO41 Tcode.

Revert if any doubt in case using above tcode.

Regards,

Tejas

Former Member
0 Kudos

Dear Teja,

If i convert thorugh CO41 all pld ord will be converted to production order with the reference of pld ord. But i need one production order for all the pld ord.

Regards,

S.Suresh.

former_member184655
Active Contributor
0 Kudos

Dear Suresh,

In my understanding its no possible to combine multiple planned orders into a single production order.

Regards

Mangalraj.S