Dear sir,

When I am confiming the production orders due to cogi error activation the orders are confirm ed without cosumpiom. materials because the BOM materials was not available in the stock.How I will consume that materials.Plz explain with t code and example.

Regards

Amar Puhan

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

To stop COGI error go to SPRO setting for Production Order Confirmation

SPRO->Production->Shop Floor Control>Oprations->Confirmation--->Define Confirmation Parameters

Select Plant and Order Type ->General and INdividual Entry>Activate Error HAndling/Logs--->1.Goods Movement

2.Terminate for incorrect Goods movts

this fields you activated.Production Order Will not confirm at the time of less stock and not maintained storage location

sundaresan_velayudam
Active Contributor
0 Kudos

After the raw material stock received

Go to T.Code# COGI

enter the period and execute

select the material and go to detail and save the goods movement, system will post the goods movement for the raw material, you can find the posted document in Co14 itself or in COOIS- automatic goods movement