on 2021 Jul 05 2:44 PM
Hi,
In "Monitor Material Coverage - Net and Individual Segments" app, we have the button "Revoke acceptance of shortages".
How can we accept the shortage for specific requirement?
Regards.
Hi Mohamadreza,
In "Monitor Material Coverage - Net and Individual Segments" app, click on the material number > Open > Check Material Coverage. It will open "Manage Material Coverage" app, click on the MRP Element (Demand). Here you have the "Accept Shortage" button available.
Best regards,
Luan