CO11N Doubt

Former Member
0 Kudos

Gurus

I want to add time during confirmation at CO11N. I know its captured & also gone to SAP Note 540734 but would like to know how to achieve this. Even OPK0 was not of much help

Hence please comment on this requirement i.e. "How to include time during confirming via CO11N"

Regards

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

Why dont you try using timesheet entry to book times of the employee and transfer it to the respective cost object ( Production order) .

Its more simple and effective

Hope this could help you.

Regards

Sarvan

Former Member
0 Kudos

HI,

In the OPK0 transaction for the push button Dates use the erea 0500 Dates : execution and forecast.

It will allow you to enter the execution start date and as well as time at the time of confirmation.

In the transaction use the Hearder erea as 0110 Confirmation/order/sequence/operation/sub-operation split .

I thing it will help you out.

regards,

kaushik

Former Member
0 Kudos

Thanks

Can we go for any user exit or so? I will try for your suggestion and revert but any other possibility than this?

Regards