Hi Friends,

in CO02- Operations overview - Dates tab or Qty/Activities tab , the planned activity values are not updated , and in co11n confirmation the actual data are not displayed ( the yield and activity duration ) only unit of measure for yield and activity are displayed

please give solution

With Regards

Arun Kumar R V

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

hi arun..

kindly see ur work center..i think u did not define activity type in work centre costing view...

plz check taht

regards

Aqueel

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

pls check whether you have entered the values for the corresponding parameters in routing and

formulas in Work center - scheduling tab page.

You can slo check the results of scheduling (ie, to see whether the planned activity values are included in scheduling ) , in CA02 routing - choose Extras - schedule and you can see the results there.

Former Member
0 Kudos

HI,

i have assigned cost center and activity type in the work center and in the routing also i have specified activity duration .

but in CA02 routing - choose Extras - schedule i am not able to see the results there.

give solution

Regards

Arun

Former Member
0 Kudos

Have you checked the formulas in Work center - scheduling tab page ?

also check the scheduling indicator has been set for the control key of the operations in OP67 ?

Former Member
0 Kudos

HI,

in Work center - scheduling tab page for processing formula sap002 and for teardown formula sap003 are given

in OP67 9control key) scheduling indicator is checked

regards

arun

Former Member
0 Kudos

Hi,

pls check whether scheduling parameters have been defined for your order type in OPU3

and ensure that the Production scheduler in OPU3 is either same as you defined in Material Master - Work Scheduling view or asterisk *.

Hope the scheduling indicator in OPU3 is flagged .

(If the indicator has not been set, lead time scheduling is not carried out)

dhaval_choksi3
Active Contributor
0 Kudos

HI,

If the activitie timing are not there in order then , it also not comes during Order confimation.

So check in workcenter. Have you define SVK parameters and Scheduling formula in workcenter?

And also check your confirmation parameters as below,

T.Code OPK0.

Go to Default Screen and,

Set Quantity and Services selection as 1 Immidiate Proposals.

Regards,

Dhaval