CO02-Date Can not be converted(Please Correct) Message No: AG011

former_member1362799
Participant
0 Kudos
1,987

Hi Gurus,

When i release a production order then i get error message- Error during availability check for order and release rejected check log.

I check the log and see the error-Date can not be converted (Please correct) message no. AG011

I have checked all things Material stocks,MRP views for checking rule-02 ,OPJK,OPJJ for order type there everything is right.

but not get the reason for this error and solution.

so please suggest me the solution for this issue.it is very urgent.

i checked some threads but not found related to pp all threads are related to SD.

Thanks in advance.

Regards,

Vivek

View Entire Topic
MarianoCabalen
Active Contributor
0 Kudos

Hi Vivek,

Something should be wrong with your factory calendar. Check your factory calendar and try extending your calendar.

Kind Regards,

Mariano

former_member1362799
Participant
0 Kudos

Hi Mariano,

I checked Factory calendar in SCAL  that is maintained from 2006 to 2015.

please can u tell me how can i extend it.

If i make any changes in Dev. server then directly all changes will be reflected to PRD. server or what.

because i read this below thing:

The calendar is not client-specific

Each change takes effect directly in all clients

BR,

Vivvek

MarianoCabalen
Active Contributor
0 Kudos

Hi Vivek,

No doubts that the problem is your factory calendar. Extend it and it will be fix.

You will have to change the Factory calendar in Development system, move the order and test in QA & and move it to prod.

In each environment you have clients, so the fact that the calendar is not client-specific means that you don't have to make your changes in your development system.

For example, you can have a landscape like this:

DEV (010): Development

DEV (900): Sandbox

QAS (010): Quality

QAS (020): Trainings

PRD (010): Productive


DEV, QAS and PRD are environments / systems / servers.

DEV 010 or DEV 900 are different clients.


Kind Regards,

Mariano



former_member1362799
Participant
0 Kudos

Hi Mariano,

Thanks for ur quick response.

Please can u guide me, how to extend a factory calendar in SCAL.

In SCAL maintained factory calendar from 2006 to 2015.

So,there i need to change only it from 2006 to 2020 or to do something else.

BR,

Vivek

MarianoCabalen
Active Contributor
0 Kudos

Hi Vivek,

Follow these screenshots. Anyway, you can find how to do it in lot of posts looking in google or even here in SCN community.

Kind Regards,

Mariano