on 2009 Jan 27 7:50 PM
Hi SAP's
In capacity leveling in CM31 (by Production order),in the order view screen they are only need REL status production order , i Don't know how to configure this one, any one Can you please help me this issue with detailed procedures,
Thanks in Advance
Eswar.
Request clarification before answering.
Dear Eshwar,
Pl. explain the requirement in detail.
In CM31, graphical view, Select order no and click on order view. It will display production order.
Release order by clicking on Flag symbol. REL will appear in Status.
it will show PRC, MANC etc indicating ur order is precosted, material availability check not done......
Hope this will help u. Revert back for further discussion.
Thanks and Regds
Sridhara K N
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
101 | |
39 | |
8 | |
4 | |
3 | |
3 | |
3 | |
3 | |
2 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.