I am a fairly new user of SAP-PS and I was wondering how to "close" an internal processing activity. A little background. My project is divided in stages and I want to make sure after stage "x" is completed that the codes I provided for labour reporting in that stage gets closed, therefore team members will no longer be able to use the code avoiding incorrect cost assignments.

Thanks

Alexander

Accepted Solutions (1)

Accepted Solutions (1)

MTerence
Active Contributor
0 Kudos

Hi Alex,

As suggested by others you need to Close the Activity.

CJ20N - Edit - Status - Close - Set.

For labour confirmation or time posting, when confirming the activity, you need to make sure Final Confirmation is checked, which gives CNF status for the activity, else it will be PCNF.

If you Tecchnically complete a activity you still be able to post labour hours, so its better to close the activity.

Regards

Terence

Answers (3)

Answers (3)

Former Member
0 Kudos

Thank you all for your help.

Alexander

sanjeevc
Active Contributor
0 Kudos

Hi,

it's depend on project type but before closing you have set TECO, FNBL if opex project then CLSD.

Regards,

Sanjeev

Paulo_Vitoriano
Active Contributor
0 Kudos

Hi Alex,

Normally, after final confirmation you would set a TECO status - Technically Completed or also known as Close technically.