cancel
Showing results for 
Search instead for 
Did you mean: 

Close STO PO

former_member229716
Active Participant
0 Kudos
3,240

Hi Guy,

My User requested to close STO (Stock Transfer Order) PO which exceeded aging more that 360 days.

My problem is that PO already been GI and Pending GR. The requested Stock has been adjusted by stock take adjustment.

I have tried to use Delivery Complete indicator in delivery tab in PO. SAP does not allow because of difference GI quantity and GR.

How can i close that STO PO ?

Kusma
Discoverer
0 Kudos
How to Short close STO

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

To close the STO, you can either:

1. Complete the STO cycle and post the GR. This will let you tick the delivery complete indicator. Then do the necessary inventory adjustments.

or

2. Cancel the GI. Tick the delivery complete indicator. Do the necessary inventory adjustments.

Former Member
0 Kudos

Hi

First of all you hv to reverse pending GR's in receving plant.

So that stock comes back to stock in Transit.

Then at supplying plant do VL09 for reversal of GI for the qty present in stock in Transit qty.

Delete the TO for that much qty and close STO by placing lock ( Not deletion) indicator on PO line item.

former_member212745
Active Contributor
0 Kudos

Unless and untill you complete the cycle of STO, This po will not be closed.

Pl. receive the material against STO po in the receiving plant, then only this po can be closed