CKMSTART and Stock upload in different Periods

zunaid_hingora2
Active Contributor
0 Kudos

Hello CO Masters , I have a question Our go live was scheduled for july so we run CKMSTART in june to upload the Materials as on 30th JUne 2017 but it was postponed and now our go live is in Aug and stock upload on 31st july what will be the impact and precautions to be taken

1.Stock upload as on 31st july

2.Run ML for June

3.Change MM period to 7

4. Run ML for July

Is this the correct approach , Should i take anything else into consideration

Accepted Solutions (0)

Answers (2)

Answers (2)

malay_vakil
Active Participant
0 Kudos

Hi,

If you upload stock in July then ML run for June is not required.

Malay

Former Member
0 Kudos

Hi Zunaid,

Your approach looks ok.but one point, are you executing standard cost estimate? If yes, before any goods movements into new period,cost estimate should be processed.

Thanks,

Rau