Dear Gurus,

While doing ck11n iam able to estimate the cost but getting an green message the message is below

DIAMOND BIKE ZMCO CK 694 No structure could be determined for internal activity 502000 (1200) 1

No structure could be determined for internal activity 500000 (1200)

No structure could be determined for internal activity 501000 (1200) 3

No structure could be determined for internal activity 502000 (1300) 7

No structure could be determined for internal activity 500000 (1300)

No structure could be determined for internal activity 501000 (1300) 9

No structure could be determined for internal activity 503000 (1400) 10

where am i going wrong?

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

if you run the assessment of direct activity repairing hour you need to reverse the assessment

Answers (2)

Answers (2)

Former Member
0 Kudos

hi,

goto KL02 open your actvity type and flag the average price check box inside the ALLOCATION DEFUALT VALUES tab.

hope this helps

regards

sayeed

Former Member
0 Kudos

HI,

check T-code OKTZ for the given cost elements in the message.