Dear all..

Our client does not require product costing.

He just intrested to run Cost estimates with Qty. Structure i.e.CK11N.

I just want to know what settings are required for that..from start to end.... from controlling area settings to costing sheet if required..

It will be better if anybody will provide configuration links or guides..

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Without product costing PP process will not complte.

Please let us know the details that why no costing?

Regards

TAJUDDIN

Former Member
0 Kudos

Hi,

CK11N normally done for repetitive manufacturing

CK24 for both discrete and repetitive manufacturing

when you do CK24 mark and release,then the standard price will be updated in the material master.

for that PP process is to after confirmation do TECO or CLOSE then you have to do settlement , WIP variance number of controlling transaction then only full cycle will be completed

Thanks

Bala

former_member196398
Active Contributor
0 Kudos

Bala,

Please review your answer... too much of conflict is there. What you have said is for PP-Discrete process not for REM.

REM uses Product Cost Collector.

Regards,

Prasobh

Former Member
0 Kudos

hi prasobh,

i said CK11N for REM only

Discrete process we do only CK24N not CK11N

Thanks

Bala

former_member196398
Active Contributor
0 Kudos

Bala,

CK11N is used both for REM & Discrete process, this is to create the material cost estimate. CK24 is used to mark and release the cost, which gets updated in the material master. We can also use CK40N to do it for more than a material.

In REM prelimenary cost estimates or Product cost collecters are created using KKF6M or KKF6N.

Regards,

Prasobh

siddheshwar_rajguru2
Active Participant
0 Kudos

HI Ranjeet,

Your client does not required prodict costing , but still he want CK11N means???

Which is your process either REM, PP or PP-PI.

In REM - repetative manufacturing there is be product costing like

1. u have product cost collector

2.production version

3. do ck11n

4.ck24

then cost is updated in the materil master of costing view.

In CK11N you are runing the cost for a materil for certain period with giving input prd version, costing lot, dates.

once Ck11N is complet then you are do Ck24 i.e marking and relase the cost.

Because of product cost collector the cost is collectd here and this cost is called priliminary cost , which is quanity structure of BOM component.

This is monthly activity and then settle the cost.

regarding to sheet, check OPN2, you are responsible to gve valuation varrient to CO consultant so that it assign into costing sheet.

CO consultant defines the REL stratyegy of costing, then over head cost parameter etc in costing sheet.

For more details plz check the SPRO settings of PRODUCT COSTING

Regards

Siddhesh