on 2009 Jun 15 2:16 PM
Hi....
Can any one plz have a look
In simple wordsim explaining.....IM Proj....NWA..WBS..FXA...FINALSETTLEMENT.
Now im seeing the CJI3 report.
Here it shows After Final Settlement, Value type is 4 (Actuall).
Whether the system behaviour is correct actually i have read it should be after settlemnt Valuetype 11
Waiting 4 inputs
Regards
Chandra
Let us know that budgeting ( availability control ) is that in your scenario,
Secondly, tell your process bit in more details. This will help us to understand situation.
Regards
Nitin P.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Nitin...................Thanx for your responce.
Let me explain.....
I have created project.....assigned Costcenter with level 1 wbs.....then i have created Cost activity(plan cost).........userstatus updated......then released project...AVAC ...... external activity.......PO...MIGO...MIRO...SETLLEMENT...NWA-WBS-FXA....created asset....final settlemnet.
then i have seen the report in cji3...value type its showing as 4(actual)....but it should be 11(Statistical actual) as value type
Regards
against the settled WBS how may cost elements you are getting ?
if you have maintained any settlement cost element seperately after doing final settlement to FXA in CJI3 you will get values against this cost element -ve and value type is 4. so it will knock off the cost against the WBS.
you will get value type 11 only if you are doing settlement to AUC and not to FXA.