CJCO do not calculate Actual amount

0 Kudos
143

Dear all

During CJCO run the program didn't take into account 2014 actuals. On specific WBS element we have some Assigned amound in 2014 (in CJ31), but in CJCO we have 0 in Actual column. As result, whole budget was carried forward to 2015 which is incorrect.

I've tried to reconstruct project info and availability control (CJBW, CJEN, CJBN), but it doesn't helped.

I've tried BPCARRYF report for analysis, but it returns error AP147.

Please advice what else can be checked?

View Entire Topic
0 Kudos

This was error in program. SAP issued correction 2124310.

Assigned points to myself ))