Dear experts,

I'm trying to copy the project actual costs to a new planning version with CJ9CS. I have some actuals linked to the project from a production order. When executing CJ9CS, the actual costs are copied (like timesheet and purchase order costs), but the costs linked to the production orders are not. I assume this is because the costs are in the production order and not in the project, which kind of makes sense to me, but I really need to be able to copy those costs to the new planning version. Is there any configuration where this can be changed? or another workaround?

Thanks in advance!

View Entire Topic
Ken_Melching
Product and Topic Expert
Product and Topic Expert
0 Kudos

That is correct, production order costs post to the production order.  PP Order costs can be moved to the WBS via Settlement.  You will have to use Non-Valuated Project Stock.  And you will not generate WIP for in-work PP orders, the costs would be an expense to the project at settlement.