Charging Time and Employee Service Cost Levels

Linne_Vermaak
Explorer
0 Kudos

Hi all, 

In Professional services, when an employee charges time to a project does it use their Service Cost Level or the rate linked to the Activity Type / role they have been assigned in the project?

Thank you

View Entire Topic
DavidTabery
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi @Linne_Vermaak,

if you have maintained a Service Cost Level in the employment of the employee as well as a cost rate for this Service Cost Level, this rate will be used. If one of those is not maintained, no Service Cost Level in the employment or cost rate for the Service Cost Level, the cost rate of the activity type/role will be used. 

For an overview on the access sequence please take a look at "Field Priority" in the help: Manage Cost Rates - Services | SAP Help Portal

Best regards,

David