on 2012 Jan 13 11:06 AM
Hi experts,
Sometimes, we create a purchase order and we distribute quantities on several cost centers.
Then, in the MIGO transaction, the distribution is made with the quantities indicated in the purchase order.
I wish I could change these quantities when receiving goods. Do you know how to do it ?
Thanks for your help !
Philippe
in OME9 make account assignment changable
from MIGO account assignment tab you can go to PO and change it in PO
probably the person doing migo need to have authorization for PO changes
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
i am not sure about cost center..
ya but we can distribute batch wise or storage location wise
and there is "Icon" distribute Qty in MIGO
Regards
kailas Ugale
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
102 | |
8 | |
8 | |
6 | |
5 | |
5 | |
4 | |
4 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.