HI

Organizational assignments are not managed as time-dependent in the asset master record.

We want to change the assignment to a cost center, which is in another PC.

The system then automatically run ABUM with appropriate standard transaction type as a default for the posting transaction.

Which standard transaction type is appropriate to reflect change in balance sheet side in PCA ?

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

The best for this is to use the transaction ABUMN - Transfer within Company Code and not to make the change with AS02