cancel
Showing results for 
Search instead for 
Did you mean: 

change work schedule

Former Member
0 Kudos
60

hi

i have one payroll area (monthly)

when i make any change in work schedule for example 01/01/08 to 05/01/08 flex& 06/01/08 to 31/12/9999

normal when i run payroll to this month 01/01/08 to 31/01/08 it consider this two period and give me two valuation (valuation 01& valuation02) and dublicate all wage type how can i controll this problem

plz help

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

hi.

u should not change it

Former Member
0 Kudos

but i implement sap in factory and this factory have ahuge labours and all the time change their work schedule in the middle of the month

Edited by: ahmed morshidy on Mar 24, 2008 1:49 PM

Answers (3)

Answers (3)

Former Member
0 Kudos

Pr Class: 10 Factoring

Gopal

Former Member
0 Kudos

yes i used pc 10 specification 1 but it not solved

Former Member
0 Kudos

hi..

system will automatically do it. This is due to change in WPBP

Former Member
0 Kudos

this is standard in sap i cant solve it?

Former Member
0 Kudos

Hello

Use processing class

Former Member
0 Kudos

which proceesing class?