on 2019 Dec 04 8:46 AM
Hi everyone,
is it possible to change the Valuation Variant in an existing Costing Variant, field in OKKN is greyed out, see attached screenshot.
The Costing Variant is existing. The Valuation Variant is existing. I only want to assign an other one.
Hallo zusammen,
wie kann man nachträglich in einer Kalkulationsvariante eine andere Bewertungsvariante hinterlegen?
Mit der OKKN ist dieses Feld bei mir ausgegraut, siehe Screenshot.
Hi Sarah,
No, you cannot change the valuation variant (and the costing type) in a saved costing variant. In other words, once a costing variant is saved, these 2 components cannot be changed.
Therefore, you may have to choose one of the following options:
Regards,
Adamu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
106 | |
8 | |
8 | |
6 | |
5 | |
5 | |
5 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.