Dear all,

How to change profit centre in material master with stock(opening balance - 561 stock ?

What are implications of changing profit centre in material master ?

Jeyakanthan

Accepted Solutions (1)

Accepted Solutions (1)

JL23
Active Contributor
0 Kudos

In standard SAP it is possible to change the profit center at any time.

However this will create inconsistencies in your profit center accounting. Hence you should issue all stock first to a cost center with 201 movement, then change the profit center, then get the material back with 202 movement.

You need to make MM335 message an error message in OMT4 to allow a change only if there is no stock

If you dont follow this way, then you create inconsistencies in profit center accounting.

Because...you received your stock without profit center (actually it is a certain default profit center), if you then change the PC in your material, then each issue will be posted to the new PC, while it never had a receipt.

subhadeep_das
Contributor
0 Kudos

Hello Jürgen L,

I would request you to pls list down the t.codes that will be required to carry on the above process you had mentioned. Pls help.

best regds

Subha

Former Member
0 Kudos

Hi Das,

The transaction is MB1A to issue stocks to a cost center.

Cheers,

Danny

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi

If you have profit center accounting active then you need to make stock zero and then only you can change. In case any account assigned transaction is open you need to close it.

Regards