on 2013 Jan 09 6:37 AM
Hi All,
I have used change profile (OPSG) in network to restrict the creation of new activities once a network is released, but system is not stopping me in doing so.
In Change Profile i have set 'E Error' for activities to be ceated in released network.
Please advice..
Thanks
Does anyone have any clue?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.