Hi Gurus,

I have two issue in ECR

1) When i try to assign an change number to the material through production version (C223) i am getting the following error message "The change number was not assigned to all entries you have selected.

Incorrect entries are still selected."

2) I have created change number for the material and i assigned that number to material through prod. version. Then when i try to create recipe through prod. version system throwing an error message " Change rule 3 assigned to the profile". I have checked all the parameters and everything is looking fine but still system throwing this error message.

Kindly help to fix the issues.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

any updates?